Portfolio Risks

Review recorded capacity, schedule, cost and commercial risks across programs.

Active risks include Open and Monitoring records.

Unassessed risks are shown separately; Unknown is not a low severity.

Active risk records
10 — Active risk records: show these records
Open and Monitoring · Projects with an active risk: 10
Active Critical risks
3 — Active Critical risks: show these records
3 projects: Project Atlas, Project Orion, Project Nova
Active risks not assessed
0 — Active risks not assessed: show these records
Unassessed risks are shown separately; Unknown is not a low severity.
Closed risk records
1 — Closed risk records: show these records
Reviewable; excluded from active counts
Filter risks

Ordered by recorded qualitative assessments only; no numerical or monetary risk score is calculated.

Showing 10 of 11 risk records · 10 projects affected

Portfolio risk register
ProjectRiskCategoryProbabilityImpactSeverityMitigationOwnerTriggerStatus
Project NovaSecurity deadline arrives before the preferred service terms are settled (open the record on its project page)CommercialModerateHighCriticalSeek a documented deadline extension or choose an explicitly authorized security position with Legal and Finance input.Jordan Ellis (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Security deadline arrives before the preferred service terms are settled
Description
Seek 300 MW in two 150 MW increments. Study and preliminary indications support the current planning dates, but no capacity-bearing agreement is executed. A $12M security deadline creates an urgent commercial decision while ESA terms remain under review.
Related decision (urgency)
Choose the security and ESA negotiation pathOct 3, 2026Upcoming
Project AtlasRoute approval now controls full-capacity delivery (open the record on its project page)ScheduleModerateHighCriticalConfirm the revised route sequence and price the alternative corridor with the utility.Avery Lin (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Route approval now controls full-capacity delivery
Description
Seek 400 MW for full service by December 2029. Utility route/permitting assumptions now move the full-service forecast to September 2030. Validate a recovery corridor before committing to a revised campus sequence.
Related decision (urgency)
Choose the route-recovery study pathOct 8, 2026Upcoming
Project OrionTransformer procurement window threatens the later 300 MW (open the record on its project page)ProcurementModerateHighCriticalValidate upgrade assumptions, obtain utility procurement milestones, and test alignment with the campus load ramp.Morgan Vale (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Transformer procurement window threatens the later 300 MW
Description
Seek 500 MW in two increments: 200 MW in September 2029 and 300 MW more after a transmission upgrade. The initial forecast is unchanged; the full-capacity forecast moved to June 2031 and company exposure rose $35M. Decide whether to advance facilities engineering while evaluating ramp alignment.
Related decision (urgency)
Authorize next-stage facilities engineeringOct 15, 2026Upcoming
Project SummitRevised facilities estimate exceeds the current illustrative budget (open the record on its project page)CostModerateHighHighSeparate scope refinement from unit-cost change and confirm the customer allocation with the utility.Casey Rowan (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Revised facilities estimate exceeds the current illustrative budget
Description
Seek 400 MW through two 200 MW increments. Phase-one capacity has agreement support; later service remains studied. Delivery forecasts are unchanged, but the company estimate rose from $65M to $100M after scope refinement. Choose a scope and negotiation position.
Related decision (urgency)
Select the facilities scope and commercial negotiation positionOct 12, 2026Upcoming
Project VectorReactive-performance mitigation is not yet selected (open the record on its project page)TechnicalModerateHighHighHave the utility and consultant compare the specified reactive support and topology options.Samir Lake (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Reactive-performance mitigation is not yet selected
Description
Seek 250 MW by December 2029. A studied voltage/reactive constraint supports a March 2030 utility forecast pending mitigation selection. A decision is due later in October; no material weekly change is recorded.
Related decision (urgency)
Select which voltage-mitigation option to advanceOct 22, 2026Later
Project HorizonScreening information does not establish a utility delivery path (open the record on its project page)CapacityModerateModerateModerateSubmit a defined load profile and obtain the utility's required study/process information.Taylor Quinn (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Screening information does not establish a utility delivery path
Description
Screen a fictional site for 500 MW. The December 2030 date is a development target only; utility timing, allocation, and company exposure are unknown. The next action is a documented utility inquiry rather than a power commitment.
Related decision (urgency)
No open decision recorded for this project
Project CedarUnreviewed study assumptions may alter the available MW or upgrade scope (open the record on its project page)TechnicalModerateModerateModerateConfirm the consultant/utility study deliverable date and review the submitted load assumptions.Riley Brooks (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Unreviewed study assumptions may alter the available MW or upgrade scope
Description
A 350 MW load request is in study. The $25M company forecast is a preliminary allowance with low confidence; no utility energization forecast has been established. Prepare the study review and confirm the load-model assumptions.
Related decision (urgency)
No open decision recorded for this project
Project KeystoneConstruction interfaces require coordinated outage and access windows (open the record on its project page)ConstructionModerateModerateModerateMaintain the utility/customer interface schedule and confirm equipment arrival against the agreed milestones.Drew Mercer (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Construction interfaces require coordinated outage and access windows
Description
The fictional 300 MW service package is under construction with executed capacity-bearing agreement support. The March 2028 forecast and $88M company exposure are unchanged. Continue interface and readiness tracking.
Related decision (urgency)
No open decision recorded for this project
Project AuroraFinal protection and commissioning evidence must be accepted (open the record on its project page)TechnicalModerateModerateModerateConfirm test records, readiness responsibilities, and the utility's energization authorization gate.Alex Arden (fictional)Recorded condition remains unresolved at the relevant delivery or commercial gate.Open
Description, evidence and related decision: Final protection and commissioning evidence must be accepted
Description
A 150 MW program is approaching commissioning and the December 15 service forecast is unchanged. Agreement-supported capacity is not yet energized. Track completion evidence and the utility's authorization conditions.
Related decision (urgency)
No open decision recorded for this project
Project MeridianDesign interfaces require routine coordination (open the record on its project page)StakeholderLowLowLowMaintain the weekly interface review.Jamie Finch (fictional)An interface owner misses an agreed response.Monitoring
Description, evidence and related decision: Design interfaces require routine coordination
Description
Residual low-severity coordination risk after access resolution.
Related decision (urgency)
No open decision recorded for this project
How to read these labels
Severity
Low; Moderate; High; Critical; Unknown
Recorded assessment, not a probability or engineering certification.
Risk status
Open; Monitoring; Closed
Open and Monitoring remain active.