Decisions Required
What needs a decision, by whom, and by when?
Reporting cutoff: October 1, 2026 · Due horizon: October 15, 2026
Open and In review decisions are unresolved. Later and undated decisions remain visible.
This register supports review and preparation only. It records no approvals and does not imply authority to commit the company.
- Unresolved published decisions
- 5 — Unresolved published decisions: show these records
- Open and In review · 5 projects
- 4 decisions due through October 15
- 4 — 4 decisions due through October 15: show these records
- 0 overdue · 0 due today · 4 upcoming
- Due after the horizon
- 1 — Due after the horizon: show these records
- Later — still open and visible · Due date missing: 0
- Resolved records
- 1
- Reviewable; outside unresolved counts
Showing 5 of 6 decision records · 5 projects
Unresolved decisions first, earliest due date first; undated decisions follow dated ones.
The table scrolls sideways to show every column; the project column stays in place.
| Project | Decision | Due date | Why it matters | MW impact | Date impact | Cost impact | Risk impact | Owner | Status | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Project Nova | Choose the security and ESA negotiation path (open the record on its project page) | Oct 3, 2026Upcoming | A $12M security requirement is due October 5; draft ESA terms do not establish a capacity commitment. | 300 MW requested; zero agreement-supported MW recorded. | October 3 decision precedes October 5 security deadline; proposed extension is unagreed. | $12M security is separate from $62M company infrastructure forecast. | Security deadline arrives before the preferred service terms are settled | Demo capital decision owner (fictional role; authority not asserted) | Open | ||||||||||||||||||||
Review options: Choose the security and ESA negotiation pathQuestion: Choose the security and ESA negotiation path? Options — proposed choices for review (3)
Options are choices for review. No approval or recommendation is recorded unless shown above.
| |||||||||||||||||||||||||||||
| Project Atlas | Choose the route-recovery study path (open the record on its project page) | Oct 8, 2026Upcoming | A route decision determines whether an alternative can be tested before the next utility design gate. | 400 MW studied; zero stronger/committed MW recorded. | Current September 30, 2030 forecast is 273 days later than December 31, 2029 target. | $1.5M proposed investigation within $98M current forecast. | Route approval now controls full-capacity delivery | Demo capital decision owner (fictional role; authority not asserted) | Open | ||||||||||||||||||||
Review options: Choose the route-recovery study pathQuestion: Choose the route-recovery study path? Options — proposed choices for review (3)
Options are choices for review. No approval or recommendation is recorded unless shown above.
| |||||||||||||||||||||||||||||
| Project Summit | Select the facilities scope and commercial negotiation position (open the record on its project page) | Oct 12, 2026Upcoming | The design package cannot be fixed until leadership selects the supported scope and negotiation boundaries. | 400 MW requested; 200 MW agreement-supported. | Current initial September 2029/full June 2030 forecasts unchanged. | $100M company forecast; $35M above prior and $20M above illustrative budget. | Revised facilities estimate exceeds the current illustrative budget | Demo capital decision owner (fictional role; authority not asserted) | Open | ||||||||||||||||||||
Review options: Select the facilities scope and commercial negotiation positionQuestion: Select the facilities scope and commercial negotiation position? Options — proposed choices for review (3)
Options are choices for review. No approval or recommendation is recorded unless shown above.
| |||||||||||||||||||||||||||||
| Project Orion | Authorize next-stage facilities engineering (open the record on its project page) | Oct 15, 2026Upcoming | The utility needs an engineering direction before reserving the next design/procurement window; engineering approval does not secure additional MW. | 500 MW requested; 200 MW agreement-supported; additional 300 MW remains studied. | Initial September 30, 2029 unchanged; full June 30, 2031 versus June 30, 2030 target. | $3M proposed engineering authorization within $115M total company forecast; forecast is $35M above prior. | Transformer procurement window threatens the later 300 MW | Demo capital decision owner (fictional role; authority not asserted) | Open | ||||||||||||||||||||
Review options: Authorize next-stage facilities engineeringQuestion: Authorize next-stage facilities engineering? Options — proposed choices for review (3)
Options are choices for review. No approval or recommendation is recorded unless shown above.
| |||||||||||||||||||||||||||||
| Project Vector | Select which voltage-mitigation option to advance (open the record on its project page) | Oct 22, 2026Later | The chosen option defines further study, cost allocation questions, and design dependencies. | 250 MW studied; zero qualifying agreement-supported MW. | March 31, 2030 forecast is 90 days later than December 31, 2029 target. | $70M company forecast; no priced alternative is recorded. | Reactive-performance mitigation is not yet selected | Demo capital decision owner (fictional role; authority not asserted) | Open | ||||||||||||||||||||
Review options: Select which voltage-mitigation option to advanceQuestion: Select which voltage-mitigation option to advance? Options — proposed choices for review (2)
Options are choices for review. No approval or recommendation is recorded unless shown above.
| |||||||||||||||||||||||||||||
How to read these labels
- Decision status
- Draft; Open; In review; Decided; Closed; Cancelled
- Only Open and In review are unresolved published decisions.
- Deadline
- Overdue; Due today; Upcoming; Later; Due date missing
- Evaluated at the fixed reporting cutoff, not today's clock.